Question: Hello, I really need help understanding how to do this. Your University is holding a fund-raiser and will be hiring a band to entertain spectators.
Hello, I really need help understanding how to do this.
Your University is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
| Activity | Description | Predecessors | Duration (DAYS) |
| A | Site Selection | None | 6 |
| B | Buy Concessions | None | 5 |
| C | Rent Facilities | None | 4 |
| D | Build Stands | A | 6 |
| E | Generator& Wiring | A | 4 |
| F | Security | B, C | 9 |
| G | Lighting Installation | E,F | 4 |
| H | Sound System | D,G | 4 |
| I | Stage Construction | H | 5 |
| J | Tear Down | H | 6 |
| K | Close Project | I,J | 2 |
1. Conduct a forward and backward pass using Activity on the Node (AON)
2. Identify the total duration of the project.
3. Identify the Critical Path