Question: Hello, please help me answer question 3 associated with this problem below Running Case You and your team are continuing your work on the Global
Running Case You and your team are continuing your work on the Global Treps Project. Your project spon- sor, Dr. K., has asked you to refine the existing cost estimate for the project so you can evalu- ate supplier bids and have a solid cost baseline for evaluating project performance. Recall that your schedule and cost goals are to complete the project in six months for under $120,000. You planned to use up to $50,000 total to pay yourself and your team members, and your initial estimates were $30,000 for travel expenses, $20,000 for hardware and software, and $20,000 for organizing four events, including consultants, legal/business fees, etc