Question: Hello! Please help me find the target completion time in weeks and the total savings. Please show work. I believe the critical path is B-D-F-G-H,

Hello! Please help me find the target completion time in weeks and the total savings. Please show work. I believe the critical path is B-D-F-G-H, and the normal completion time is 36 weeks. Not sure what to do from here. Thanks.

You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are$1,500 per week.

Hello! Please help me find the target completion time in weeks and

a. What would be your target completion week? The target completion week is week (Enter your response as an integer.) b. How much would you save in total project costs with your schedule? Total Savings =$ . (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!