Question: help asap According to earned value analysis, the SV and status of the project described below is - PV=$2,200EV=$2,000AC=$2,500BAC=$10,000 a. $300; the project is ahead

 help asap According to earned value analysis, the SV and status

help asap

According to earned value analysis, the SV and status of the project described below is - PV=$2,200EV=$2,000AC=$2,500BAC=$10,000 a. $300; the project is ahead of schedule b. $200; the project is behind schedule c. +$8,000; the project is on schedule d. +$200; the project is ahead of schedule