Question: help Asap please Customers are served in a process with two resources A worker in the first resource serves 083 customers per hour and a

help Asap please help Asap please Customers are served in a
Customers are served in a process with two resources A worker in the first resource serves 083 customers per hour and a worker in the second resource serves 0.48 customers per hour. The first resource has 1 worker and the second resource has 2 workers Demand occurs at the rate 112 customers per hour Instruction Round your answer to 1 decimal place, What is the utilization (%) of the second resource