Question: Help ASAP Problem 7-1 (Algo) An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.6 minutes, and the

Help ASAPHelp ASAP Problem 7-1 (Algo) An analyst has timed

Problem 7-1 (Algo) An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.6 minutes, and the standard deviation was 1.26 minutes for a worker with a performance rating of 126 percent. Assume an allowance of 26 percent of job time. Find the standard time for this operation. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Standard time minutes