Question: Help me with the following CPM optimization problem A contractor requests the execution of a particular project. The activities and resource estimation are summarized in

Help me with the following CPM optimization problem

A contractor requests the execution of a particular project. The activities and resource estimation are summarized in the following table. The figures are in monetary units and the duration in days. The indirect costs of the project are estimated at $60.00 per day.

Activity

Predecessor Activity

Normal Time

Normal Cost

Crash Time

Crash Cost

A

--

6

100

2

500

B

--

5

300

4

700

C

A

7

500

7

800

D

B

2

150

2

650

E

C

6

200

1

350

F

C

9

80

8

250

G

D, E

3

90

3

125

H

F

9

90

9

160

a) The normal duration of the project and its total cost. b) The minimum duration of the project and its total cost. c) The optimal duration of the project and its total cost. d) If the contract specifies that the project must be completed in 20 days, what is the total cost for that delivery time?

Why do they say that activity G and H is wrong?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!