Question: Help me with the following PERT problem please :( A contractor requests the execution of a particular project. The activities and resource estimation are summarized

Help me with the following PERT problem please :(

A contractor requests the execution of a particular project. The activities and resource estimation are summarized in the following table. The figures are in monetary units and the duration in days.

Activity
Predecessor Activity
to tm tp
A ---- 20 31 45
B ---- 14 28 38
C A 18 36 43
D B 32 52 100
E B 24 32 63
F B 6 16 28
G F,D 4 18 40
H E,G 8 20 36
I E,G 18 34 42
J C,H 4 16 24

Determine: a) The probability of completing the project in 130 days. b) The probability of completing the project if you are granted 12 additional days. c) The number of additional days that must be requested if you want to have a 90% probability of completing it on time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!