Question: help me with the steps for this solution Suppose that General Foundry has been implored to install the new equipment in 8 weeks instead of

help me with the steps for this solution Suppose that General Foundry has been implored
to install the new equipment in 8weeks instead of
16weeks. Assume that General Foundry is given
a bonus of $600for each week that the project
completion time is crashed.
The critical path for the project is 15weeks.
What options does the firm have?
The normal and crash times and costs are shown in
Table 12.9.
Crash costs are assumed to be linear and Figure 12.11
shows the crash cost for activity B.
Crashing activities B and A will shorten the
completion time to 14but it creates a second
critical path.
Any further crashing must be done to both critical
General Foundry
Normal and Crash Data for General Foundry, Inc.
ACTIVITY
TIME (WEEKS)COST ($)CRASH
COST PER
WEEK ($)
CRITICAL
PATH?NORMAL CRASH NORMAL CRASH
A 2122,00023,0001,000Yes
B 3130,00034,0002,000No
C 2126,00027,0001,000Yes
D 4348,00049,0001,000No
E 4256,00058,0001,000Yes
F 3230,00030,500500No
G 5280,00086,0002,000Yes
H 2116,00019,0003,000Yes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!