Question: help needed and work explanation The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations,
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Suppose that Rafay is only given 9 weeks (instead of 12 ) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration