Question: Help, please Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C A D A

Help, please Problem 5-10 (Algo) The followingHelp, please

Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C A D A E B F C,D G D, E H TIMES (DAYS) a m b 1 4 7 2 3 7 3 5 7 5 6 10 1 2 6 1 3 6 1 3 14 2 5 14 F,G b. What is the critical path? OA-D-F-H O B-E-G-H O A-C-F-H O A-D-G-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Project completion time days