Question: Help solve this as fast as possible EARNED VALUE REPORT Cumulative-to-date Variance At Completion WBS # BCWS BCWP ACWP SCHED COST BUDGET L. EST. VARIANCE

Help solve this as fast as possible
EARNED VALUE REPORT Cumulative-to-date Variance At Completion WBS # BCWS BCWP ACWP SCHED COST BUDGET L. EST. VARIANCE 301 800 640 880 -160 -240 2,400 2,816 -416 Answers are provided in the Answers section at the back of the book. 1. Is the task ead or behind schedule? By how much? 2. Is the task overspent or underspent? By how much? 3. When the task is completed, will it be overspent or underspent? Date of Measurement Project Value and Cost Cost Varance CV-EV-AC Harta Actual Cost Planned Value Schedule Varianca SVEEV.PY Earned Value Time ScheduleStep by Step Solution