Question: help Use this table as inputs to answer the questions below: Activity Duration (months) Total Budgeted % Complete Predecessors Cost ($) after 3 months A
Use this table as inputs to answer the questions below: Activity Duration (months) Total Budgeted % Complete Predecessors Cost ($) after 3 months A 2 12,000 100 B 3 15,000 75 C 2 8,000 80 D 3 A 6,000 50 E B 10,000 0 F E 7,500 G 2 A 4,000 0 If data from timesheets and other accounting records indicate that the actual amount of money spent on the project so far (i.e. at the end of 3 months) is $31,000, determine the following for the entire project: A. Cost variance B. Schedule variance C. Time variance D. Cost performance index E. Schedule performance index F. The estimated cost at completion (i.e., new budget) G. The estimated time at completion (i.e., new duration) Be sure to provide appropriate interpretations for each answer. 2 4 0