Question: Help Using the following project information The critical path is A-C-E-G-I-J. The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be
Help


Using the following project information The critical path is A-C-E-G-I-J. The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 32 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.) P( project 32)= (b) Calculate the probability that the project will be completed in 36 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.) P( project 36)=
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
