Question: Using the following project information The critical path is A - C - E - G - I - J . ( a ) Calculate

Using the following project information
The critical path is A-C-E-G-I-J.
(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, e.g.1.7945.)
P(project 31-
(b) Calculate the probability that the project will be completed in 34 weeks. (Round your answer to 4 decimal places, e.g.1.7945.)
P(project 34
 Using the following project information The critical path is A-C-E-G-I-J. (a)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!