Question: Herbert Slant is developing a program in supply chain management certification for managers. Slant has listed a number of activities that must be completed before
Herbert Slant is developing a program in supply chain management certification for managers. Slant has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s) Time (days)
A - 2
B - 5
C - 3
D B 10
E A, D 5
F C 6
G E, F 8
b) The critical activities for the leadership training program development project are
c) The project length for the leadership training program development project = ? days
d) Slack time for each of the activities is:
Activity Slack
A ?
B ?
C ?
D ?
E ?
F ?
G ?