Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity
Immediate Predecessors
Timedays
A
minus
B
minus
C
minus
D
B
E
A D
F
C
G
E F
This exercise contains only parts b c and d
Part
b The critical activities for the leadership training program development project are
A E G
C F G
B D E G
Part
c The project length for the leadership training program development project
enter your response here
days.
Part
d Slack time for each of the activities is:
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
This exercise contains only parts b c and d
b The critical activities for the leadership training program development project are
c The project length for the leadership training program development project days.
d Slack time for each of the activities is:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
