Activity
Immediate Predecessor(s)
Time(days)
A
minus
33
B
minus
66
C
minus
33
D
B
1010
E
A, D
44
F
C
55
G
E, F
1010
This exercise contains only parts b, c, and d.
Part 2
b) The critical activities for the leadership training program development project are
A - E - G
C - F - G
B - D - E - G
.
Part 3
c) The project length for the leadership training program development project=
enter your response here
days.
Part 4
d) Slack time for each of the activities is:
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
This exercise contains only parts b,\( c \), and \( d \).
b) The critical activities for the leadership training program development project are
c) The project length for the leadership training program development project \(=\) days.
d) Slack time for each of the activities is:
Roger Ginde is developing a program in supply

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!