Question: Here are the data for a time - cost CPM scheduling model analysis. The time is in days and the costs include both direct and

Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None 32 $ 200 $ 400
B A 43 $ 300 $ 600
C A 11 $ 200 $ 200
D B and C 32 $ 500 $ 550
E D 21 $ 500 $ 900
What are the total time of this project and total normal cost?
Multiple Choice
Total time is 13 days, total cost is $1,200.
Total time is 12 days, total cost is $1,700.
Total time is 11 days, total cost is $1,600.
Total time is 10 days, total cost is $1,750.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!