Question: Here are the data for a time - cost CPM scheduling model analysis. The time is in days and the costs include both direct and
Here are the data for a timecost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None $ $
B A $ $
C A $ $
D B and C $ $
E D $ $
If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?
Multiple Choice
Total time is days, total cost is $
Total time is days, total cost is $
Total time is days, total cost is $
Total time is days, total cost is $
Total time is days, total cost is $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
