Question: Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs

Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs If you crash this project to reduce the total time by one day, what is the total time of the project and total cost? Multiple Choice Total time is 13 days, total cost is $1,500. Total time is 12 days, total cost is $2,000. Total time is 12 days, totol cost is $2,300. Total time is 11 days, total cost is $1,850. Total time is 11 days, total cost is $2,350