Question: Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.

Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.

Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None 3 2 $200 $400
B A 4 3 $300 $600
C A 1 1 $200 $200
D B and C 3 2 $500 $550
E D 2 1 $500 $900

What are the total time of this project and total normal cost?

Multiple Choice

  • Total time is 13 days, total cost is $1,200.

  • Total time is 10 days, total cost is $1,750.

  • Total time is 12 days, total cost is $1,700.

  • Total time is 11 days, total cost is $1,600.

  • Total time is 9 days, total cost is $1,700.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!