Question: Here are the following parameters for a Project: EV = $ 5 5 , 0 0 0 AC = $ 4 5 , 0 0

Here are the following parameters for a Project:
EV = $55,000
AC = $45,000
PV = $50,000
CPI =1.2
BAC = $100,000
Forecast the Project Cost at Completion (EAC) if the remaining work on the project is done at the same rate of efficiency as the work performed so far.