Question: Question text Here are the following parameters for a Project: EV = $ 1 1 3 2 8 4 AC = $ 1 2 0

Question text
Here are the following parameters for a Project:
EV = $113284
AC = $120,000
PV = $92,000
CPI =0.9
BAC = $200,000
Forecast the Project Cost at Completion (EAC) if the remaining work on the project will be done according to its budget.