Question: Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-F-D A-B-C-D A-E-G-C-D b. How many weeks will the project

 Here is a CPM network with activity times in weeks: a.
Determine the critical path. A-E-F-D A-B-C-D A-E-G-C-D b. How many weeks will

Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-F-D A-B-C-D A-E-G-C-D b. How many weeks will the project take to complete? c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration