Question: Here is a CPM network with activity times in weeks: a. Determine the critical path. multiple choice A-E-G-C-D A-E-F-D A-B-C-D b. How many weeks will
Here is a CPM network with activity times in weeks:
a. Determine the critical path.
multiple choice
-
A-E-G-C-D
-
A-E-F-D
-
A-B-C-D
b. How many weeks will the project take to complete?
c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?