Question: Here is a CPM network with activity times in weeks: A network diagram flowchart. The flows are as follows. A ( 7 ) , B
Here is a CPM network with activity times in weeks:
A network diagram flowchart. The flows are as follows. A B C and D A E G C and D A E F and D
Determine the critical path.
multiple choice
ABCD
AEGCD
AEFD
How many weeks will the project take to complete?
Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?