Question: Here is a CPM network with activity times in weeks: A network diagram flowchart. The flows are as follows. A ( 7 ) , B

Here is a CPM network with activity times in weeks:
A network diagram flowchart. The flows are as follows. A (7), B (5), C (6), and D (6). A (7), E (4), G (3), C (6), and D (6). A (7), E (4), F (8), and D (6).
Determine the critical path.
multiple choice
A-B-C-D
A-E-G-C-D
A-E-F-D
How many weeks will the project take to complete?
Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?