Question: here is a CPM network with activity times in weeks: Here is a CPM network with activity times in weeks: (B(5) C(6) (A(7) G(3) D(6)

here is a CPM network with activity times in weeks: here is a CPM network with activity times in
here is a CPM network with activity times in
Here is a CPM network with activity times in weeks: (B(5) C(6) (A(7) G(3) D(6) (E(4) (F(8) a. Determine the critical path. O A-E-F-D A-E-G-C-D O A-B-C-D b. How many weeks will the project take to complete? Number of weeks 18 c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? Number of weeks reduced

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!