Question: Here is the master schedule record: Complete the following master schedule record. Click the icon to view the master schedule record. Complete the master production

Here is the master schedule record:

Complete the following master schedule record. Click the icon to view the master schedule record. Complete the master production schedule (enter your responses as whole numbers). \begin{tabular}{lcccccccc} \hline On-hand inventory at end of week 1: 85 & 10 & & & & & \\ \hline Week & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 \\ \hline Forecasted demand & 50 & 60 & 70 & 50 & 80 & 60 & 70 & 75 \\ Booked orders \end{tabular}