Question: here was responsibility on both sides for system performance and service delivery. How did all of this happen? Phase 1 of UCMS ( wage records

here was responsibility on both sides for system
performance and service delivery. How did all of this
happen?
Phase 1 of UCMS (wage records) was implemented
in May 2008. Phase 2, which included the employer
tax portion of the system, went live in March 2011
but required additional work, which took years to fix.
Phase 3 for benefit claims processing, payment, and
appeals continued to lag behind with problems and
ultimately never went live.
In 2012, DLI enlisted the Carnegie Mellon
Software Engineering Insitute to conduct an independent assessment of the UCMS. The study was
completed in July 2013, and recommended continuing work on remaining Phase 2 problems, but stopping work on Phase 3. Many of the problems it identified for Phase 3 could not be solved.
The Carnegie Mellon study found many flaws in
the systems development process. IBM had extensive
systems experience and technology knowledge but
its proposal underestimated the projects scope and
complexity. DLI lacked sufficient staffing and experience for effective oversight and management of the
contract and project. There was no formal delegation
of roles and responsibilities for managing the project.
No one at DLI was held accountable. DLI essentially
relied on the contractor to self-manage.
UCMS was considered a large-scale software project due to its complexity, large number of information requirements and business rules, and its cost.
DLIs solicitation for vendor proposals for UCMS
exhibited ambiguity in communicating all of these
requirements, and also neglected to define and describe quantitative and qualitative performance measures and metrics for the proposed system.
A large-scale software-intensive system such as
UCMS requires a rigorous and disciplined testing
strategy, but this was not implemented. IBM decided to use DLI users to help develop test scripts.
They provided the business expertise, but IBM did
not use IT test experts on its end. User acceptance
testing was initiated before completing system tests
for Phase 2 and Phase 3. Rigorous testing came too
late in the project. DLI did not specify a minimum
of metrics for UCMS system performance so that
there were no identifiable criteria and evidence for
The Pennsylvania Department of Labor and
Industry (DLI) is responsible for the administration and operation of the states unemployment compensation program, which provides
temporary income to replace lost wages for qualified workers. DLI employs over 500 people and
has approximately 200 offices statewide to serve
Pennsylvanias 6.4 million workers and nearly
300,000 employers. Unemployment compensation
(UC) claims are usually filed online or by telephone
or mailed to a UC service center.
DLI had a legacy mainframe system for processing
unemployment benefits that was over 40 years old.
However, it became increasingly expensive to maintain and difficult to modify, with limited functionality for case management and integrating newer tools
and technologies to enhance productivity.
In June 2006, DLI awarded IBM a fixed price contract totaling $109.9 million for the Unemployment
Compensation Modernization System (UCMS), which
would replace the antiquated mainframe system.
The initial contract with IBM called for more modern
and efficient technology and business processes for
(1) maintaining wage records, (2) processing employer taxes, and (3) claims processing, payment,
and appeals, to be completed by February 2010. IBM
won the UCMS contract after a three-year bidding
process, claiming to be the only vendor with the type
of proprietary databases capable of supporting a totally integrated computer system.
However, this project experienced significant
delays and cost overruns, ultimately costing nearly
$180 million, with much of the system never completed when the contract expired in September 2013.
By that time, the project was 45 months behind
schedule and $60 million over budget. Pennsylvania
taxpayers had paid IBM nearly $170 million for what
was supposed to be a comprehensive, integrated, and
modern system that it never got. IBMs contract was
not renewed. In March 2017, Pennsylvania sued IBM
for breach of contract, fraudulent and negligent misrepresentation, and charging taxpayers for services
it did not provide. IBM said Pennsylvanias claims
had no merit and that it would fight the lawsuit. A
spokesman for the company laid some of the blame
for the projects problems on the state, saying that
Pennsylvanias Unemployment Compensation
Modernization System: Unfinished Business
CASE STUDY
Chapter 14 Managing Projects 561
transfer of essential knowledge for the entire project,
a loss of project memory. Since the UCMS projects
start, 638 different contractors and staff members
worked on the project. The majority of the project
workforce spent less than one year on the projec

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!