Q3. Proceed to solve the following problem by Critical Path Method. (20) Name of Activity Immediate Predecessors Activity Time in Days None 5 B None Z+1 A Y+1 D A X+6 E A Z+4 F E 4 G DF 10 H B,C 8 GH 2 Find out the following: a. Sketch the whole network. b. Find out critical path by analyzing and showing ES, EF, LS, LF and float in a table. Find out the project completion time. C