Question: Q3. Proceed to solve the following problem by Critical Path Method. (20) Name of Activity Immediate Predecessors Activity Time in Days A None 5 B

Q3. Proceed to solve the following problem by

Q3. Proceed to solve the following problem by Critical Path Method. (20) Name of Activity Immediate Predecessors Activity Time in Days A None 5 B None 4 A 3 D 7 E 7 F E 4 G DF 10 H B,C 8 GH 2 Find out the following: a. Sketch the whole network. b. Find out critical path by analyzing and showing ES, EF, LS, LF and float in a table. C. Find out the project completion time