Question: Here's the project schedule: Task Description Duration Predecessor (Days) Tasks A Determine user 5 requirements B Data collection 7 A C Feasibility analysis A D

 Here's the project schedule: Task Description Duration Predecessor (Days) Tasks A

Here's the project schedule: Task Description Duration Predecessor (Days) Tasks A Determine user 5 requirements B Data collection 7 A C Feasibility analysis A D System documentation 5 B E Management presentation 1 B, C F System design 8 D, E G Purchase hardware 10 F H Write application code 10 F Test system 6 G, H