Question: Hey experts I would really appreciate some help with this question, I will thumbs up asap :) The Wonder Works Company for rubber supplies has
Hey experts I would really appreciate some help with this question, I will thumbs up asap :)
The Wonder Works Company for rubber supplies has this table that shows their activity, as well as the optimistic, realistic, and pessimistic duration to finish the activity (number of days)

Use the information given to calculate the expected number of days for each of the activities
Draw the network of activities
What is the critical path and expected time to complete the entire project. Determine the earliest and latest start time, earliest and latest finish times, and the slack time. Write them in a atable
Immediate Predecessors Activity A B D E F G H I J K B,D A.E A,E F G HI Optimistic 4 2 1 6 2 6 1 3 10 14 6 Duration (Days) Realistic 6 4 2 7 4 10 2 6 11 16 8 Pessimistic 8 6 3 8 6 14 3 9 12 18 10