Question: Hi I need help with this question please? Christmas Express makes wreaths in batch sizes of 16. The cutting and assembly process takes 6 minutes
Hi I need help with this question please?

Christmas Express makes wreaths in batch sizes of 16. The cutting and assembly process takes 6 minutes per wreath, and the decorating process time is 11 minutes per wreath. It takes 3 minutes to move the wreaths from the cutting and assembly process to the decorating process. 3. Compute the value-added, non-valueadded, and total lead times of the wreath process. Valueadded lead time minutes Non-value-added lead time: Move time Withinbatch wait time Total lead time mlnutes |U|Ull H b. Compute the value-added ratio. Round to one decimal place. /o
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts