Question: HI, I really need help on this problem, please answer asap. Utilizing a constant workforce strategy and assuming each worker can produce one unit in
HI, I really need help on this problem, please answer asap. Utilizing a constant workforce strategy and assuming each worker can produce one unit in 1.25 hours, with an 8-hour workday, use the information below to determine staffing levels for the first six months of the new year.

How many people should we employ for the entire 6 months, rounded up to the nearest whole number?
What would the efficiency of these workers be in January, as measured by what they *do* produce compared to what they *could* produce? Please report your answer as a whole number percentage (i.e., 57% instead of 0.57).
In which month (using the abbreviations in the table) would the workers be most efficient?
What is one positive outcome from the constant workforce example, and one negative outcome from the constant workforce example?
Month Forecasted Demand No. of Production Days Jan 400 21 Feb 750 20 Mar 895 23 300 22 Apr May 600 21 Jun 450 22Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts