Question: hi please assist with the below project management question The following information relates to a project you are working on: Activity Predecessor Optimistic time Most
hi please assist with the below project management question
The following information relates to a project you are working on:
| Activity | Predecessor | Optimistic time | Most likely time | Pessimistic time | Expected |
| In days | |||||
| a | - | 3 | 6 | 8 |
|
| b | - | 2 | 4 | 4 |
|
| c | - | 1 | 2 | 3 |
|
| d | a,b | 6 | 7 | 8 |
|
| e | c | 2 | 4 | 6 |
|
| f | e | 6 | 10 | 14 |
|
| g | e | 1 | 2 | 4 |
|
| h | d | 3 | 6 | 9 |
|
| i | g,h | 10 | 11 | 12 |
|
| j | f,g | 14 | 16 | 20 |
|
3.1 Calculate the expected completed time for each activity. (10)
Note that in practice you always round the number up to the next full number since you create extra slack time for the project team.
3.2 Construct the network diagram (AON). (10)
3.3 Identify the paths and indicate the critical path. (5)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock