Question: hi please assist with the below project management question The following information relates to a project you are working on: Activity Predecessor Optimistic time Most

hi please assist with the below project management question

The following information relates to a project you are working on:

Activity

Predecessor

Optimistic time

Most likely time

Pessimistic time

Expected

In days

a

-

3

6

8

b

-

2

4

4

c

-

1

2

3

d

a,b

6

7

8

e

c

2

4

6

f

e

6

10

14

g

e

1

2

4

h

d

3

6

9

i

g,h

10

11

12

j

f,g

14

16

20

3.1 Calculate the expected completed time for each activity. (10)

Note that in practice you always round the number up to the next full number since you create extra slack time for the project team.

3.2 Construct the network diagram (AON). (10)

3.3 Identify the paths and indicate the critical path. (5)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!