Question: Hi! Please encode your solution. Zebastian Builders, Inc. employs the cost-to-cost method in determining the percentage of completion for revenue recognition. The company's records show

Hi! Please encode your solution.

Zebastian Builders, Inc. employs the cost-to-cost method in determining the percentage of completion for revenue recognition. The company's records show the following information on a recently completed project for a contract price of Php15,000,000.

2019 2020 2021
Costs incurred to date 2,700,000 9,150,000 ?
Gross profit (loss) 300,000 1,050,000 (150,000)

  1. The percentage of completion in 2019.
  2. The estimated costs to complete the project on December 31, 2020
  3. The actual cost incurred during the year 2021.
  4. Revenue recognized in 2020.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!