Question: Homework 2 PART 1 . Below is the sales data for Forever Young Boutique between March of Year 1 and July of Year 5 .

Homework 2
PART 1.
Below is the sales data for Forever Young Boutique between March of Year 1 and July of
Year 5.(You can find the Excel sheet containing this data on Blackboard.)
Month Year 1 Year 2 Year 3 Year 4 Year 5
January 6381.0711016.5511965.6810580.74
February 4405.838264.1412761.9813420.87
March 4566.49126.956843.9518126.734476.27
April 6941.8910970.4520109.6819092.919108.79
May 7047.2310189.2811148.6415384.0118109.54
June 6784.377043.858365.41223713743.6
July 5814.236717.379469.0813252.5318339.25
August 6906.389139.721022113819.77
September 8075.1311315.1915161.4121755.64
October 7913.5610838.417731.0824838.1
November 9054.1811150.9417508.9915955.6
December 14114.5817592.227566.8919370.7
1) Develop a forecast for the sales in August of Year 5 by using three different forecasting
techniques: Three-month simple moving average, Weighted moving average with weights 0.5,
0.3,0.2(the weight 0.5 is given to the most recent observation), and Exponential smoothing
method with a smoothing constant of 0.3.(15 points)
2) Which forecasting method you considered in Question 1 is the most accurate according to the
Mean Absolute Deviation (MAD) criterion? Please justify your answer. (5 points)
3) Calculate a 95% confidence interval of the forecast made for August of the fifth year. While
developing the confidence interval, use the forecasting method identified in question 2 as the
most accurate one. (5 points)
4) Do you see any major peculiarities in the sales data that were not captured by the forecasting
methods in Question 1?(5 points)
PART 2.
5) What strategies do supermarkets, airlines, hospitals, banks, and cereal manufacturers use to
influence demand? Please provide ONE strategy for each and explain that strategy in 1-2 sentences.
(15 points)
6) Schedule the following activities using CPM:
Activity Immediate Predecessor Time (Weeks)
A -1
B A 4
C A 3
D B 2
E C, D 5
F D 2
G F 2
H E, G 3
a) Draw the network (5 points)
b) What is the critical path? (5 points)
c) How many weeks will it take to complete the project? (5 points)
d) Which activities have slack, and how much? (5 points)
7) NORAN Inc. is a fabrication and assembly shop that produces radios, each of which consists
of two identical electronic receiver boards and an aluminum chassis. These components are put
together in radio assembly. The electronic boards are obtained from a supplier who has a oneweek
delivery lead-time. The aluminum chassis is fabricated internally and the fabrication leadtime
is one week. The lead-time for assembling the radio is also one week. Only one shipment of
completed radios is made in a week, at the beginning of the week.
Radio
Assembly
Lead
Time:
1
week
Electronic Boards
Lead
Time:
1
week
Used:
2
per
radio
Chassis
Lead
Time:
1
week
Used:
1
per
radio
It is the beginning of week 1. NORAN is planning fabrication and purchasing based on the
master schedule shown below. (The only relevant weeks are those numbered 4,5,6 and 7.) The
master schedule requires 50 radios to be shipped at the beginning of week 4, another 50 to be
shipped at the beginning of week 5, and so forth. There are currently 10 electronic boards, and no
chassis units or assembled radios, in inventory.
a) Using MRP logic, determine the schedule of planned order releases for radio assembly,
electronic board purchase, and chassis fabrication that is required to meet the radio shipping
master schedule. (20 points)
Radio Shipping Master Schedule
Week 1234567
Radio Shipment 000505010080
Radio Assembly Requirements
Week 1234567
Requirements
Initial Inventory
Scheduled Receipts
Planned Order Release
Electronic Board Requirements
Week 1234567
Requirements
Initial Inventory
Scheduled Receipts
Planned Order Release
Chassis Fabrication Requirements
Week 1234567
Requirements
Initial Inventory
Scheduled Receipts
Planned Order Release
b) NORAN employees work 40 hours per week. Currently a single worker performs both chassis
fabrication and radio assembly. Fabrication of each chassis takes 20 minutes, and assembly of a
radio also takes 20 minutes. Show that under the plan you generated in part (a), the capacity of
the worker is exceeded in at least one week. Furthermore, show how the chassis fabrication plan
devised in part (a) can be modified so as to meet the master schedule requirements without
exceeding the worker's capacity, and without changing the plans for electronic board purchase or
radio assembly. (15 points)
Chassis Fabrication Requirements
Week 1234567
Requirements
Initial Inventory
Scheduled Receipts
Planned Order Release
Assembly Ops from
part (a)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!