Question: Homework: Assignment 9 - Ch. 3 Question 2, Problem 3.6b Part 1 of 2 HW Score: 0%, 0 of 14 points O Points: 0 of

Homework: Assignment 9 - Ch. 3 Question 2,

Homework: Assignment 9 - Ch. 3 Question 2, Problem 3.6b Part 1 of 2 HW Score: 0%, 0 of 14 points O Points: 0 of 1 Save In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Immediate Predecessor(s) Activity A Time (days) 7 A 2 A 4 B 5 B 5 I - 5 G 2 C E, F D G H 3 7 a) The activities on the critical path are Help me solve this Video Get more help Clear all Check