Question: B) The standard time for this process = ? (round your response to two decimal places) Peter Rourke, a loan processor at Royal Bank, has

B) The standard time for this process = ? (round your response to two decimal places)
Peter Rourke, a loan processor at Royal Bank, has been timed performing four work elements, with the results sho in the following table. The allowances for tasks such as this are personal, 7%; fatigue, 12%; and delay, 3%. a) The normal time for the complete operation is minutes (round your response to two decimal places)