Question: = Homework: GRADED - HW 2: Ch 3 numerical HW Score: 33.33%, Points: 0 of 1 What is the minimum cost of crashing the following

= Homework: GRADED - HW 2: Ch 3 numerical <

= Homework: GRADED - HW 2: Ch 3 numerical HW Score: 33.33%, Points: 0 of 1 What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL COST CRASH COST ACTIVITY IMMEDIATE PREDECESSOR(S) NORMAL TIME (DAYS) 8 7 CRASH TIME (DAYS) 7 6 Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) 6 6 4 4 400 1,100 700 900 1,200 550 1,300 800 1,250 1,950 A, B 9 6 The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $ (enter your response as a whole number)