Question: Homework: HW 0 9 Question 6 , Concept Q What is the result of adjusting gross requirements for inventory on hand and scheduled receipts? A

Homework: HW 09
Question 6, Concept Q
What is the result of adjusting gross requirements for inventory on hand and scheduled receipts?
A. net requirements plan
B. lead time
C. master production schedule
D. gross material requirements plan