The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.
\table[[,TIME (hours)],[Job,Machine A,Machine B],[a,16,5],[b,3,13],[c,9,6],[d,8,7],[e,2,14],[f,12,4],[g,18,14],[h,20,11]]
Click here for the Excel Data File
a. Determine a sequence that will minimize makespan time.
The sequence is
b. Find machine B's idle time.
Idle time hours
c. For the sequence determined in part a, how much would machine B's idle time be reduced by splitting the last two jobs in half?
New idle time
hours, savings of
hours.
 Homework: Scheduling (i Soved Help Save & Exit Submit Check my

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!