Question: Draw the network diagram by using AON technique for the following activities, define the located activities on the critical path, define the total project
Draw the network diagram by using AON technique for the following activities, define the located activities on the critical path, define the total project duration, and find all of ES, EC, LS, LC, TF, and FF. Activity Preceding Activity Time, (Weeks) A 9. B C C A 5 D , , 4 E A 6. F E 11 G C,D H D, E 10 ,, G 12 J D,G, H K G,I,J 10 , , F 13 M H,J,L 14 J,K, M 9.
Step by Step Solution
3.53 Rating (167 Votes )
There are 3 Steps involved in it
O H WO O o Answer AON DIAGRAM 14 20 27 39 9 14 L12 39 49 ES EC C5 28 34 1... View full answer