Question: Consider the following project information. a. Draw the network diagram for this project. b. Specify the critical path. c. Calculate the slack for activities A
.png)
a. Draw the network diagram for this project.
b. Specify the critical path.
c. Calculate the slack for activities A and D.
d. What happens to the slack for activity D if A takes fiveweek?
Activity Activity Time (weeks) Immediate Predecessor(s) A, B D, C , F, G 12
Step by Step Solution
3.42 Rating (161 Votes )
There are 3 Steps involved in it
a The AON diagram is b The critical path is BEGH which takes 29 week... View full answer