Draw the network diagram by using AOA technique for the following activities, define the located activities on the critical path, define the total project
Draw the network diagram by using AOA technique for the following activities, define the located activities on the critical path, define the total project duration, and find all of ES, EC, LS, LC, TF, and FF. Activity Precedent Activity Time (Week) A 7 --- B A, D, H , D, H 5 C 4 A E A C, D, E , F F G 4 H A 8. I H 7 J G, I
Step by Step Solution
★★★★★
3.39 Rating (140 Votes )
There are 3 Steps involved in it
Step: 1
LO4 E13 L15 3 E0 16 E 3...Get Instant Access with AI-Powered Solutions