Question: Homework:Chapter 7B HW Question 2, Problem 2 Part 3 of 3 Part 1 The following information is known about a project to upgrade a point-of-sale
Homework:Chapter 7B HW
Question 2, Problem 2
Part 3 of 3
Part 1
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel:
| Activity | Activity Time (days) | Immediate Predecessor(s) |
| A | 7 | |
| B | 4 | A |
| C | 5 | A |
| D | 3 | B, C |
| E | 3 | D |
| F | 6 | E |
| G | 8 | E |
Part 2
a. Choose the correct network diagram for this project

Part 4
b. Determine the critical path and project duration.
The critical path is path
Upper A dash Upper C dash Upper D dash Upper E dash Upper G
A-C-D-E-G and the project duration is 26 days. (Enter your response as an integer.)
Part 5
c. Calculate the slack days for each activity.
(Enter your responses as integers.)
| Slack (days) | |
| Activity | |
| A | enter your response here |
| B | enter your response here |
| C | enter your response here |
| D | enter your response here |
| E | enter your response here |
| F | enter your response here |
| G | enter your response here |
PLEASE HELP I DONT KNOW HOW TO GET THE SLACK DAYS?
Homework: Chapter 7B HW Question 2, Problem 2 Part 3 of 3 CA B. B Start IT Finish S coo B Help me solve this View an example Get more help A KIV
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts