Question: Homework:Chapter 7B HW Question 2, Problem 2 Part 3 of 3 Part 1 The following information is known about a project to upgrade a point-of-sale

Homework:Chapter 7B HW

Question 2, Problem 2

Part 3 of 3

Part 1

The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel:

Activity

Activity Time

(days)

Immediate Predecessor(s)

A

7

B

4

A

C

5

A

D

3

B, C

E

3

D

F

6

E

G

8

E

Part 2

a. Choose the correct network diagram for this project

Homework:Chapter 7B HW Question 2, Problem 2 Part

Part 4

b. Determine the critical path and project duration.

The critical path is path

Upper A dash Upper C dash Upper D dash Upper E dash Upper G

A-C-D-E-G and the project duration is 26 days. (Enter your response as an integer.)

Part 5

c. Calculate the slack days for each activity.

(Enter your responses as integers.)

Slack

(days)

Activity

A

enter your response here

B

enter your response here

C

enter your response here

D

enter your response here

E

enter your response here

F

enter your response here

G

enter your response here

PLEASE HELP I DONT KNOW HOW TO GET THE SLACK DAYS?

Homework: Chapter 7B HW Question 2, Problem 2 Part 3 of 3 CA B. B Start IT Finish S coo B Help me solve this View an example Get more help A KIV

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!