Question: Answer question 2 only 2 . The following information is known about a project to upgrade a point - of - sale system at Kids

Answer question 2 only
2. The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel.
\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[A,7,-],[B,2,A]]
\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[C,4,A],[D,4,B, C],[E,4,D],[F,3,E],[G,5,E]]
a. Draw the network diagram for this project.
b. Determine the critical path and project duration.
c. Calculate the slack for each activity.
3. A project for improving a billing process has the following precedence relationships and activity times:
\table[[Activity,Activity Time (weeks),Immediate Predecessor(s)],[A,3,-],[B,11,-],[C,7,A],[D,13,B, C],[E,10,B],[F,6,D],[G,5,E],[H,8,F, G]]
 Answer question 2 only 2. The following information is known about

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!