Question: Homework:Homework: Chapter 14 Question 2, Problem 14.3 Alternate Part 2 of 2 HW Score: 52.08%, 1.56 of 3 points Score: 0.56 of 1 Save As
Homework:Homework: Chapter 14
Question 2, Problem 14.3 Alternate
Part 2 of 2
HW Score: 52.08%, 1.56 of 3 points
Score: 0.56 of 1
Save
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base,
1
spring,
and
4
clamps. The base is assembled from
1
clamp
and
1
housing.
Each clamp has
1
handle and
1
casting.
Each housing has
1
bearing
and
1
shaft.
There is no inventory on hand.
This exercise contains only parts b and c.
The product structure is as follows:
A rectangle at the top center is labeled Bracket. Three branches originate from this rectangle and connect the rectangle to three rectangles. The first rectangle is labeled Base (1), the second rectangle is labeled Spring (1), and the third rectangle is labeled Clamp (4). Two branches originate from rectangle Base (1) and connect the rectangle to two other rectangles labeled Clamp (1) and Housing (1). Two branches originate from rectangle Clamp (4) and connect the rectangle to two other rectangles labeled Handle (1) and Casting (1). Two branches originate from rectangle Clamp (1) and connect the rectangle to two other rectangles labeled Handle (1) and Casting (1). Two branches originate from rectangle Housing (2) and connect the rectangle to two other rectangles labeled Bearing (1) and Shaft (1).
Bracket
Base(1)
Clamp(1)
Handle(1)
Casting(1)
Spring(1)
Housing(1)
Shaft(1)
Clamp(4)
Bearing(1)
Handle(1)
Casting(1)
b) Determine the gross quantities needed of each item if you are to assemble
125
brackets.
| Base: | 125125 units(enter your response as a wholenumber). |
| Spring: | 125125 units(enter your response as a wholenumber). |
| Clamp: | 625625 units(enter your response as a wholenumber). |
| Housing: | 125125 units(enter your response as a wholenumber). |
| Handle: | 625625 units(enter your response as a wholenumber). |
| Casting: | 625625 units(enter your response as a wholenumber). |
| Bearing: | 125125 units(enter your response as a wholenumber). |
| Shaft: | 125125 units(enter your response as a wholenumber). |
c) Compute the net quantities needed if there are
30
of the base and
75
of the clamp in stock.