Question: Hours Queue time Wait time Process time Move time Inspection time The throughput time (manufacturing cycle time) is: Multiple Choice 65 hours O 29 hours.


Hours Queue time Wait time Process time Move time Inspection time The throughput time (manufacturing cycle time) is: Multiple Choice 65 hours O 29 hours. O 41 hours. C 63 hours